Spain
Renewables & Storage Systems
2025

Battery Energy Storage Integration in Gibraltar’s Power Grid

Circet led the development of the Gibraltar BESS project at North Mole Power Station, a strategic initiative designed to strengthen the stability and sustainability of the territory’s electricity grid. The project involved the installation of a Battery Energy Storage System (BESS) to modernize local energy infrastructure and support the transition to a lower‑carbon energy system.

PROJECT SNAPSHOT
Location
North Mole Power Plant, Gibraltar, Spain
Solution
Renewables & Storage Systems
Circet Energy's Role
Civil, mechanical and electrical works for a BESS
16 MW / 16 MWh
Installed storage capacity
8
Battery groups installed
2024-2025
Project duration
THE CHALLENGE

Gibraltar’s energy infrastructure required modernization to improve grid stability, reduce reliance on diesel‑based generation and support the decarbonization of the local energy system. Strengthening resilience while ensuring reliable power supply was a key challenge for the territory.

Our approach

Deploying battery storage to modernize the grid

Replacing auxiliary diesel generation with battery storage

The project consisted of installing a Battery Energy Storage System (BESS) to replace auxiliary diesel generators with high‑capacity battery storage solutions that are safer, more efficient and more environmentally-friendly.

Integrated civil, mechanical and electrical works

We carried out civil, mechanical and electrical works, including the installation of battery containers, power conversion systems and a medium‑voltage substation as part of the overall BESS infrastructure.

Connection to strategic power infrastructure

The BESS infrastructure was connected to North Mole Power Plant, as well as to the Water Port and S36 distribution centers, ensuring seamless integration into Gibraltar’s electricity network.